Date |
Event |
November 2013 |
- MSCHE Self-Study Institute
|
December 2013 |
- Steering Committee Identified
|
January 2014 |
- Approved Timetable;
- Self-Study Design Selected
|
February 2014 |
- Steering Committee Kick Off;
- Working Groups Identified
|
March 2014 |
- Working Groups (WG) Defined;
- Research Questions Approved;
- Self-Study Design Document Completed;
- Self-Study Design to Dr. Guerrero
|
April 2014 |
- Visit by Dr. Tito Guerrero,
- Working Groups Kick Off
|
May 2014 |
- Self-Study Kick Off- University Wide
|
June 2014 |
|
July 2014 |
|
August 2014 |
|
September 2014 |
- Campus Feedback on WG Data
|
October 2014 |
|
November 2014 |
|
December 2014 |
- Data Cut-Off Point;
- Campus Feedback on WG Data
|
January 2015 |
- WG Analyze and Summarize Data;
- Reports to Steering Committee;
- MSCHE Selects Team Chair;
- Dates for Site Visit and Preliminary Visit Set
|
February 2015 |
|
March 2015 |
|
April 2015 |
|
May 2015 |
- First Draft of Self-Study
|
June 2015 |
- MSCHE Selects Team: MU Approves
|
July 2015 |
|
August 2015 |
|
September 2015 |
- University Community Reviews Self-Study Draft
|
October 2015 |
- Preliminary Visit by Chair
|
November 2015 |
|
December 2015 |
|
January 2016 |
- Final Self-Study sent to Team
- Compliance Report Sent to Team
|
February 2016 |
|
March 2016 |
|
July 2016 |
|